Report
About the construction and repair work carried out by the engineering company

In accordance with the Resolution of the President of the Republic of Uzbekistan dated December 28, 2020 №4936 "On measures to develop social and industrial infrastructure of the Republic of Uzbekistan in 2021-2023", the construction of the Presidential School in Nurafshan of Tashkent region is carried out by the organization Gold Step Invest LLC.

In order to carry out construction and repair work with the general contractor, contracts worth 84,461 billion soums have been signed, to date, construction and installation work worth 59,803 billion soums (71%) has been carried out and 64,182 billion soums (76%) were financed by the customer. At present, the facility is being renovated and it is planned to complete the construction and repair work by the end of October.